Tuesday, July 28, 2009

Letter from AIMSU & ICLS on Dibang project


July 13, 2009

Mr. Jairam Ramesh,
Honorable Minister of State (Independent Charge), Environment & Forests,
New Delhi.

Sub: Illegal public hearing called for 3000 MW Dibang Multipurpose
project on August 6th; reject pre-construction clearance to project

Dear Mr. Ramesh,

Greetings from the Dibang Valley, Arunachal Pradesh! We write to you
on behalf of the Idu Cultural and Literary Society (ICLS) and the All
Idu Mishmi Students Union (AIMSU). ICLS is the apex body of the Idu
Mishmi community, while AIMSU is the students union. We would like to
bring to your notice a serious subversion of environmental norms by
NHPC and the Arunachal Pradesh state government while announcing the
public hearing for the 3000 MW Dibang Multipurpose project on August
6th.

As mentioned on the MoEF website, NHPC has applied for Scoping under
the Environment Impact Assessment (EIA) notification 2006 for the
Dibang project on May 28th, 2009. As per the EIA notification 2006 it
is clear that if the site is felt inappropriate on environmental and
social grounds, the MoEF based on recommendations of the EAC can
reject a project at this stage itself. The EAC may choose to conduct a
site visit in order to give its recommendations and could also choose
to give detailed Terms of Reference (ToR) for conduct of EIA studies
for the project and a clearance for pre-construction activities. It
is only after the MoEF conveys its decision to the project authority
after the Scoping stage that further steps such as ‘Public
Consultation’ may require to be taken up. That too only if
pre-construction clearance has been granted and necessary studies have
been conducted as per the ToR provided to the project authority as per
EIA 2006.

As per the MoEF website: “This proposal was considered by the EAC at
its meeting held on 16th June 2009. Additional information sought by
the committee.” Therefore it is clear that the EAC and MoEF are yet
to arrive at a final decision on whether to grant or reject
pre-construction clearance to the project. This is further confirmed
from the agenda for the upcoming July 24th EAC meeting uploaded on the
MoEF website which has the Dibang project listed as “Reconsideration
for ToR.” However, an advertisement has appeared on June 24th 2009 in
the Echo of Arunachal Pradesh, announcing a public hearing to be held
in the Dibang Valley district, on July 29th, 2009. This has been
subsequently been pushed ahead by ten days for August 6th. Therefore
a request for conduct of this public hearing would have gone from NHPC
to the Arunachal Pradesh State Pollution Control Board (APSPCB)
certainly before June 23rd, without any decision from the MoEF about
whether it plans to grant or reject pre-construction clearance! Even
if the MOEF was to grant pre-construction clearance at a later date,
studies will have to be undertaken as per the ToR granted by EAC. Such
completed studies will have to be available at least one month before
the public hearing to members of the public. However, both NHPC and
the APSPCB appear to have treated the Dibang project as a fait
accompli and announced the public hearing even before waiting to hear
from the MoEF about its final decision on the Dibang project at the
Scoping Stage! This is a serious subversion of environmental norms and
should not be allowed by your ministry. The public hearing scheduled
for August 6th should be cancelled with immediate effect.

Larger concerns

We believe that the public hearing process has become a mere cosmetic
step while granting rubber stamp environmental clearances and
appreciate the concerns you have raised in this respect recently. In
January 2008, NHPC and the Arunachal Pradesh state government misled
the PMO and got the Prime Minister to lay the foundation stone of the
Dibang project even before the public hearing processes and green
clearances were obtained. We are encouraged by the fact that you have
raised this issue (laying of foundation stones by project authorities
before green clearances) in a recent press conference held in New
Delhi.

One of the biggest threats to proper environmental decision-making on
Arunachal dams in recent times has been what you identified as a ‘MoU
virus’ in May 2008, in your earlier capacity as Minister of State for
Power. There has been a rapid signing of MoUs by Arunachal Pradesh,
both with the private sector and the public sector, even as it plans
to build 135 large hydel project. Each of these agreements is
accompanied by huge monetary advances to the government even before
the DPR is prepared, public consultations held and green clearances
obtained. For example, NHPC paid the Arunachal Pradesh government Rs.
225 crores while signing MoUs for three projects, including Rs. 150
crores for the Dibang project. How can we expect the EIA reports
commissioned by project authorities to give a honest picture when they
have already made huge investments upfront at the time of signing
MoUs? They are going to justify the project as ‘benign’ under any
circumstances. Similarly, the state government has already received
huge money upfront. This fact is going to clearly influence the
content of the forest clearance application it submits to the central
government or the manner in which it conducts public hearings under
the environmental clearance process.

The same saga continues at the stage of environmental appraisal. In
spite of Arunachal Pradesh being an ecologically and culturally
sensitive region (traversed by two global biodiversity hotspots:
Himalaya and Indo-Burma), as well as being seismically active, the
current EAC has granted clearances (pre-construction or environmental
clearance as the case may be) to every single project which come
before the committee! This is incredible! Although there are several
ministries looking at social justice issues (e.g. Ministry of Tribal
Affairs), the environmental clearance process handled by the MoEF is
the only space where detailed social impact assessment of large
development projects is supposed to be done (including public
consultations). Therefore, it assumes great significance for tribal
communities such as the Idu Mishmis. We are more than a little
surprised to see that even though these projects have mega impacts on
landscapes which are home to minority indigenous communities like
ours, there are no independent experts from the social sciences on the
EAC. While we respect the expertise of the current EAC members in
their respective disciplines, we would like to point out that the
current EAC is incompetent in assessing complex socio-cultural issues,
such as the impact of mega dams on the rights and livelihood of
indigenous communities like ours, as is evident from their
decision-making over the last two years in states such as Arunachal
Pradesh and Sikkim. We would urge you to ensure that both independent
social scientists as well representation from ministries such as
Tribal Affairs is necessary on the EAC. Since the Northeast is a
unique region and identified as a major area for new large hydro
projects, we would also like persons who understand the environmental
and social realities of the region to be part of such an expert
appraisal committee.

A public hearing was held for the Dibang project earlier in Roing,
Lower Dibang Valley district, in January 2008 (as per the earlier EIA
regime). During this hearing we had clearly pointed our opposition to
the destructive Dibang project and raised concerns about the shoddy
EIA reports prepared to justify the project. There is no point
holding public consultations when everything in the environmental
decision-making process until now seems to treat the Dibang project as
a fait accompli. Therefore, the people of the Dibang Valley have
boycotted/ blocked all subsequent attempts to hold a public hearing in
the Dibang Valley district. Except for a small political elite who
stand to gain personally from the mega investments in the Dibang dam,
the majority of people in the Dibang Valley have opposed this project
which stands to threaten our social and ecological security.

Scrap Dibang project at Scoping State itself

We urge the MoEF to take a precautionary principle approach and scrap
the Dibang dam at the Scoping Stage itself. We have already written
to you with a demand to declare the Dibang Valley an ecologically
sensitive area under the EPA, in which only ecologically and
socio-culturally sensitive development should be allowed, not large
dams. We want the Dibang river to flow free. By all counts the Dibang
Valley qualifies to be declared ecologically sensitive (details in our
application sent earlier). For example, renowned wildlife expert from
the Northeast, Dr. Anwaruddin Choudhury says: "Dibang and Lohit
valleys contain some of the last large contiguous tracts of tropical,
subtropical and temperate forests in the country. These forests have
potentially large populations of many rare species such as Hoolock
gibbon, Slow loris, Capped langur, Stump-tailed and Pig-tailed
macaques, Asiatic black bear, Malayan bear, Gaur, Takin, Leaf deer,
lesser cats, Clouded leopard and perhaps a good Tiger population. Also
many endemic and threatened birds. Many proposed dams in the area
means that no river basin has been spared to retain its pristine
glory. The downstream impact in the Brahmaputra plains could seriously
jeopardise common people's livelihood."

The population of the Idu Mishmi community is only 12,000. The kind
of development being proposed through multiple mega-hydel projects
involving the influx of a large number of outside labour (outnumbering
the locals) is contradictory to the constitutional and legal
safeguards provided to the small populations of culturally sensitive
indigenous communities of Arunachal Pradesh. The current safeguards
disallow land transfer to outsiders and regulate entry of persons in
our traditional homelands. But the current dams juggernaut will simply
dismantle this protection given to us.

We are putting down some of the issues which clearly indicate that a
precautionary principle approach is adopted and the Dibang project
scrapped at this stage itself:

Huge loss of forests and biodiversity: Over 5000 hectares of pristine
forests to be lost directly in the project. You are aware that the
Northeast is traversed by two of three global biodiversity hotspots
which cover India – Himalaya and Indo-Burma. Contrary to claims of the
company that no sanctuary is affected, there will be a major impact on
the Mehao sanctuary. The road to the dam site from Roing passes
through the Mehao sanctuary at certain places. Curently there is very
low traffic density on this road. The coming in of such a large
project will dramatically increase the flow of traffic of vehicles and
machinery for a long period of time (it is a long gestation project)
through the sanctuary. Such a massive dam involves the extraction of
approximately 32 lakh truckloads (193 lakh cubic metres) of boulders
and 16 lakh truckloads (96.5 lakh cubic metres) of sand from the river
bed (Dibang and some its tributaries). The river beds from where this
will be done are part of an Important Bird Area (IBA) – Dibang Reserve
Forest and adjacent areas - identified by the Bombay Natural History
Society (BNHS) as per international criteria. This IBA has also been
found to qualify to be a potential Ramsar site – a wetland of
international importance – by the BNHS in a recent publication on
potential Ramsar sites in the country.

Major demographic changes and socio-cultural impacts:

As indicated earlier the Idu Mishmi community is only 12,000 in
number. The old EIA report of the Dibang project states that 5800
people (labour and technical staff) will come in for the project
related activities. This seems to be a gross underestimate. The 2000
MW Lower Subansiri project being developed by the same company, NHPC,
is relatively smaller in all respects compared to 3000 Dibang MW –
height of dam, power generation, construction period etc. The EIA
report done for this project states that the total workforce (labour
and technical staff) during peak construction activity of 4-5 years
will be 15, 500 people. In a smaller project, the estimate was
15,500. How is it only 5,800 in Dibang? If one compares with Lower
Subansiri, the workforce in Dibang will be at the very least 25,000
(more than twice the population of the Idu Mishmis) staying for long
periods of time since this is a long gestation project. In addition,
the government is proposing a total of 17 large hydel projects in our
valley! Cumulatively, this will involve at least 150,000 outside
labour for long periods of time. The pressure on the rich forests of
the region due to such a large work force has to be accounted for too.
Despite fancy claims in project documents how fuel will be supplied to
the workforce, this is almost never complied with. A glaring example
is the 2000 MW Lower Subansiri project by NHPC. The pressure on the
surrounding forests (part of the Subansiri Important Bird Area) due to
illegal fuelwood collection by labour for the dam has also been
recorded in the monitoring reports of the MoEF’s regional office in
Shillong. Local green groups from North Lakhimpur have also reported
poaching by the labour force. In addition to the forests officially
diverted for the project, such pressures on surrounding areas will
also conflict with our traditional rights to these forests.

Project affected areas and persons is considerably higher than projected:

One of the major arguments made in favour of large hydroelectric
projects in Arunachal Pradesh is that there is relatively ‘small
displacement’ by submergence as compared to other parts of the
country. But a careful perusal of the ground situation indicates that
displacement is grossly underestimated both individually and
cumulatively. Shifting agriculture (jhum) is a dominant traditional
land use in the hills of Arunachal Pradesh and plays a critical role
in the livelihoods of people, maintaining agricultural biodiversity
and providing food security. Increasing pressures on land have
resulted in the shortening of jhum cycles (the length of the fallow
period between two cropping phases), thus impacting the ecological
viability of this farming system. The submergence of land by hydel
projects will further shorten the jhum cycle and enhance the pressure
on the surrounding areas, thus affecting the environment and the
livelihoods of jhum dependent communities over a much larger
landscape. In addition to the submergence, land use restrictions will
also apply in the Catchment Area of the reservoir as per mandatory
norms to reduce the siltation and increase the life of the reservoir.
The figures for the Dibang dam indicate that 4009 hectares will be
under submergence by the project. But the direct catchment area is
59,811.88 hectares (out of which 10, 281.64 hectares is degraded
forest/abandoned jhum and 3851.64 hectares is agriculture/current
jhum/habitation). The Catchment Area Treatment (CAT) will involve
land use restrictions in the direct draining catchment to reduce
siltation. What will be the population of people affected by this
restriction of land use in the direct draining catchment of 59, 811.88
ha? This is considerably larger than just the population affected by
loss of land in submergence zone.

Further, compensatory mechanisms required as per forest laws to
offset the loss of forests due to the project also lead to supposed
‘protection’ of other areas by change of tenure and access regimes to
land and resources. For example, conversion of Unclassified State
Forests (USFs) in AP, with currently greater access and control of
local communities, into Protected Forests, with greater state control.
Firstly, no compensatory afforestation can compensate the loss of
such a large area of biodiverse forest in the Dibang Valley.
Secondly, the compensatory afforestation will require twice the area
of forest land used directly in project (i.e. over 10,000 hectares) to
be converted from USFs to PFs, thus involving further acquisition of
rights from people.

Further, the whole issue of downstream impacts has been completely
ignored! Recent times have also seen grave concern being expressed
about the poorly studied downstream livelihood and ecological impacts
of large dams in both Arunachal Pradesh and neighbouring Assam. The
concerns include loss of fisheries, changes in beel (wetland) ecology
in the flood plains, agricultural losses, increased flood
vulnerability due to massive boulder extraction from river beds and
sudden water releases from reservoirs in the monsoons. But this issue
has been completely ignored by the MoEF and its EAC, although this has
been brought to the notice of the EAC repeatedly in the last two
years. All ToRs prescribed for Arunachal dams have been asked to
restrict their studies to only 10 km. downstream of the projects.
In the case of the Dibang project the extraction of 32 lakh truck load
of boulders (the first line of defence against floods) and 16 lakh
truck loads of sand will put the downstream areas at grave risk. It
will be judicious not to make such massive interventions in the
Eastern Himalayan rivers such as the Dibang.

As seen above, the impact on local communities and the environment is
well beyond what is being projected in the current decision-making
process.

Keeping the above issues in mind, we strongly urge you to scrap the
3000 MW Dibang Multipurpose project at the Scoping Stage itself.
Adoption of a precautionary principle approach is urgently required at
this point of time. We do not want the country’s tallest dam (288 m
high, approximately a 100 storey high building!) to come up in its
seismically most active region in our Dibang Valley. We cannot
compromise our social and ecological security under any circumstances.
While the MoEF considers this appeal to reject the pre-construction
clearance to the Dibang project, we hope you will call for an
immediate cancellation of the illegal public hearing announced for
August 6th.

Thanking you,
Sincerely,
Dr. Mite Lingi, General Secretary, Idu Cultural and Literary Society
Tone Mickrow, General Secretary, All Idu Mishmi Students Union
Raju Mimi, Information and Publicity Secretary, All Idu Mishmi Students U
nio

Read more...

Monday, March 16, 2009

No Dam Zone in Dibang Valley


Press release note (14th March 2009)

Campaign on demanding `No Dam Zone in Dibang Valley'
Today on the day of March 14, 2009 which is observed all over the world as International Day of Action against Dams and for Rivers. water and Life', we the All Idu Mishmi Students Union and Idu Mishmi Cultural and Literary Society demand Dibang Valley to be declared as an Ecologically Sensitive Zone according to the provisions under Section 3 of the Environment Protection Act, 1986 similar to that of the Aravalli hills where mining is banned.


Similarly, mega projects such as dam building should be banned in Dibang Valley and the region declared as 'No Dam Zone. A letter to this effect has been sent to the Prime Minister with copies to the officials of the Ministry of Environment & Forests and to the state Government of Arunachal Pradesh. A copy of the same is attached here with the release note.

The International Day of Action against Dams and for Rivers, Water, and Life was inspired and mandated by the participants of the 1997 First International Meeting of People Affected by Dams in Curitiba, Brazil. Every year on March 14, people around the world celebrate victories such as dam removal and river restoration, teach others about issues threatening rivers and communities, and demand improvements in policies and practices of decision-makers.


Dr Mite Linggi
Secretary
Idu Mishmi Cultural and Literary Society


Tone Mickrow
Secretary
All Idu Mishmi Student Union

Read more...

Friday, March 13, 2009

OPEN LETTER TO PRIME MINISTER OF INDIA


To
Dr. Manmohan Singh
Prime Minister of India
South Block
New Delhi


Honourable Prime Minister Sir:
For the past one year, we, the Idu Mishmis of Dibang Valley, have been subjected to a very cruel circus of development. Development that we understand very little, projects of national interest that do not evoke any interest within us, dreams that we know will remain unfulfilled.

The 3,000 MW Dibang Multipurpose Project along with more than a dozen other hydro projects are being imposed on us in the name of national interest and energy security. We have protested since we failed to be convinced that they will benefit us, we have submitted memoranda with the hope that we will be heard, and we argued against our destruction, the bleak future of our future generation, because we thought that we were the citizens of the world’s biggest democracy.

But, the events of the past one year, a sham process of forcible public participation to legitimize a project, a shoddy and incomplete environment impact assessment by a reputed public sector organization and repeated violations in organizing public hearings – all point to the fact that nobody is interested to listen to us – the governments, the bureaucrats or even our elected public representatives. Even you chose to inaugurate the Dibang Valley project early this year, some hundreds of kms away in Itanagar, without any consultation with our community.

We fail to understand how projects could be envisaged to be of national interest when their likely impacts are going to unleash destruction and devastation – destruction of our pristine forests, rich biodiversity, our land and livelihood, our sacred Taloh (as Dibang river is referred to by the Idu Mishmis) and its riverine ecology. Where an influx of 6,000 outsiders for a single project in a valley of fast diminishing 12,000 indigenous people is seen as a cultural integration and assimilation, submergence of our ancestral land and the only habitations in an otherwise hostile terrain is supposed to pave the way for a 43 km long reservoir, which will result in a ‘navigable waterway connecting the villages’, and destruction of land and livelihood is countered with generation of wage employment, all other arguments favouring the projects come to us as a cruel joke.

If these are mere apprehensions, let us also be clear that our apprehensions are still to be cleared beyond doubt. Instead, this genre of development, with the spectre of crores of rupees coming in to a mostly non monetised economy, dreams of an incomprehensible but quality life is dividing our small community and sowing seeds of divide and discord.

A future social conflict within our Idu Mishmi community could be self defeating and the Government of India will have to squarely take the blame.

Honourable Prime Minister Sir, a Public Hearing in New Anaya, Upper Dibang Valley has been again notified for March 27th, 2009, perhaps for the seventh or eighth time. This never ending circus has to end some where.

We don’t want any project in Dibang Valley, and
No further Public Hearings

This is the Will of the Idu Mishmis, the indigenous people of Dibang Valley. Your Government, being an important member of the United Nations, cannot violate the Convention on the Rights of the Indigenous People which your Government has ratified in September 2007.

We sincerely hope that our voice will reach you and your Government.

For Peace, Tranquility and Hope in Dibang Valley


Sincerely,
Idu Mishmi Cultural and Literary Society
All Idu Mishmi Students Union
Dam Affected Citizens Committee

[as posted in Veracity - a local daily of roing ]

Read more...

Wednesday, September 24, 2008

Dam updates - Roing Woes !


I'ad asked Raju Mimi, editor of Veracity( local daily of Roing ) to tell me few points about the meeting, few members of AIMSU ( All Idu Mishmi Students Union ) along with some delegates from Roing, had with the Chief Minister of Arunachal ( Mr.Khandu ). This team of delegates were accompanied by former CM of Arunachal, current Rajya Sabha MP, Mr.Mukut Mithi.

So below is what Raju responded back me with ( source: Idu mishmi community, Orkut )


Our meeting with CM n Mithi sir was not a success...
However...the points we got them to listen was..

-The state govt is loosing its independent decision making policy owing to huge financial investments in this dam building process.

-Why bargain with people for sake of NHPC? And why cant the govt bargain with NHPC for the people?

-Theres nothing like Dibang Project being of national importance. Its only the politics of business. Many auto, cement, steel and other companies want their goods to be sold, so dams has to be built.

Mithi's Response:

-If people don't want dams then there can be no dam. But the govt needs to appoint an expert committee to study the facts.
-Downstream people are not project affected.
-expressed unawareness of such large scale destruction before the project was initiated.
- Not having dams is also not a solution.
-I want our boys to each individually, in their own capacity strongly fight for our rights.
-otherwise we are already a minority...we will stand nowhere in the future...
-theres no point condemning our leaders but we must make them understand the situation. we need collective effort.
-taking part in our social activities for two years, i realised our community is very weak financially and academically. Even to celebrate our own festivals, the community cannot even mobilise Rs 1 Lakhs rupees. Its only when Mithi or Umbrey or NHPC gives donation.

-Whereas Nyshis can easily mobilise crores of rupees for their festivals,,forget about lakhs....
-ANSU, NES and all other Nyishi afiliated organisations can also easily mobilise crores of rupees.



And What Mr.Raju had to say on this: - What our concerted efforts needs to be is: 

We are so exploited that to become leaders we have to ignore our own community and appeal other community. That's how the policy went wrong and our leaders have only exploited our own people. That's why today there's not even a crorepati or academicians, intellectuals, bureaucrats or even a A class contractor in our community.

....Our young generations can no more look for state govt for employment since no one is there to help us....either compete at national level or dare to be different."

-Dorjee Khandu is CM now->Power Secy is from his community->Principal Advisor is from his community->Principal Secy is from his community->Contractor for NHPC is his family members->recently he appointed many of his community people to the post of officers in various department in Arunachal.

--Under his leadership Tawang has got all the centres attention and even tibetan refugee issue has died out. Remember some Monpas i have met are not comfortable calling themselves as arunachali whn they are out of arunachal. rather they like call themselves as Tibetan.
-Theres no point of talking of development if our own Idu people cannot decide for their future. Its time to make our community strong. Our people becoming CM or MP or MLA or Lt Governor is of no use when our community cannot strongly defend their rights. (Wangcha Rajkumar was shot dead in his own hometown, remember if our leaders neglect our own community then same fate may fall on our leaders. So make the community strong, only then our own community will protect us.)

------------------------------------------------------------------------------------------


I certainly couldn't understand with the point that, "Not having Dam is also not the option"...

What can one make of it?
The idea of people deciding for themselves simply gets killed.

Read more...

Wednesday, September 10, 2008

Are we next?

Since its inception the Chixoy, Guatemala's largest dam, has generated more ills than electricity. Unwilling to put up with more, on September 8, 500 Maya Indians seized control of it and threatened to cut off power supplies. The protests also sent out warning signals to the government which has only recently announced plans to build more such large new dams — including two on the Chixoy River itself.

The 500 protesters largely comprised survivors of the brutal army massacres carried out more than 20 years ago. "No new dams can be built until they right the wrongs done to the people of Chixoy,' said protest leader Juan de Dios, voicing the demands of his peers. Dios said the
dam's main turbines would be shut off unless the government met community leaders.

The Chixoy produces 275 megawatts of energy, accounting for 60 per cent of Guatemala's electricity. Located in the Mayan highlands, the dam has been controversial ever since development plans were first drawn up in the midst of bitter army repression during Guatemala's 36-year civil war. In 1980, the army and
paramilitaries killed 300 people from the village of Rio Negro, upstream from the proposed dam, after they refused a relocation offer.

The survivors are also seeking compensation from the World Bank, the main funding body that had aided the dam's construction. Even after an internal review had confirmed the atrocities, the bank continued to support the project, claim the angry Mayans.

(courtesy: indiaenvironmentportal )


When will the time come to realize that, there are far better avenues we can work out together to make things better for Arunachal. Now, did we ever believe Politicians and their chamchas could work wonder... Do we have to believe them this time as well?
A question we certainly should be asking ourselves.

Read more...

Saturday, May 10, 2008

Update 1: Dams:the Damned!

Now that we know our potential, 3 and a half hydro power projects per month. So does that imply we need to build Dams after another.

Getting back to the statistics, The economically exploitable hydropower potential in India through various schemes of Dam has been assessed to be at a staggering figure of 84,044MW at 60 percent load factor- which is about 148,000 MW installed capacity.
The North East part of India has the biggest share in it, with estimated 59,000MW capacity. And Arunachal Pradesh has its Lion share of more than 50,000MW. Thats a whopping figure and hard to digest fact, given the seismic vulnerability of this region.
Mind it, the whole North East region is categorized under seismic 5 zone of India.

How the whole thing started ?
In may 2003, the Prime Minister of India launched the "50,000MW Hydroelectric Intiative.(courtesy :
Indiahydro). Through this initiative, pre-feasibility reports for 162 new hydroelectric projects across 16 states with proposed capacity of over 50,000MW are to be implemented by the end of 12th five year plan(2017).
Some more comparative statistics:
1. 162 projects in 16 states for 50,000MW initiative, thats the envisaged plans.
2. 72 out of this 162 in North east itself, with total capacity of 31,885MW.
3. 42 schemes within Arunachal Pradesh, with 27,293 MW capacity.

No wonder, Arunachal certainly epitomizes the mini power house for the entire nation, and an obvious ruling, the centre of attraction for the Big hydro power players.

How can politics be left behind, isn't it ?



April 2005 : PM announces the North East Water Resource Authority on the line of the US tennessee valley authority (
know them ?)as an Independent corporation. TVA had the world bank's support.
All the 6 other states of NE accepted the draft, except for the Arunachal Pradesh. AP govt, feared that this would ultimately place the rights to river systems under TVA.
November 2005: Arunachal Pradesh Chief Minister , Gegong Apang comes up with the state's Hydro power policy to counter that.

Apang government invites Private players to the states with their proposals for Dams. On the other hand there was NHPC(National Hydroelectric Power Corporation) one of the biggest public sector in India, which was losing its projects, supposed to be alloted by Central govt.

Within short span of time, many projects were surfacing. The year 2005-06, saw 5 mega projects with Detail Project Reports being placed, and all of them Private companies.
They were namely : Tato-II(700MW) & Siyom(1000mw) --Reliance Energy
Hirong(500mw) & Lower Siang(1600mw) -- Jaypee associates
Naying (1000mw) -- DS construction

What next, Within a year, 9 new agreements were also placed on the table, totalling a capacity of 4425mw. Companies sharing this were Bhilwara, Mountain fall, KSK electricity Financing & GMR Energy.

The public sector comapanies (NHPC, NEEPCO etc) were soon losing the battle to grab their pie.

Ousting Apang, as the CM was the only probable solution that they could see. With Congress in power at the Centre, a political turmoil in Arunachal Pradesh was expected.
Finally, Gegong Apang had to quit as CM in 2007. We were supposed to make guesses that maybe, misappropriation of wealth, not so new for Apang, could be the reason for this change in Chief ministership.
Well, we by now, should know who did this. And no prizes for guessing!!
Power minister during Apang's regime, Dorjee Khandu was appointed the new Chief minister. Things would go smooth for NHPC from now on, thats something expected nothwithstanding.

Thats the problem with our mindset - Arunachali mindset or Indian mindset. We give up easily.
But, I know NHPC won't have it that easily from Dibang valley people.

So much for the sake of NHPC, our votes doesn't count. Ya, where's our vote ? Hmmm... thats the uncanny part of being in a democracy plagued by corrupted people, who sell their own people just for the sake of some amount.
Or maybe our Oldies are so much worried about their political career. Ya, they inspire us, Career is everything even when its time to retire and rest. We should rest, and not let other rest.


Will update later.

Read more...

Friday, May 09, 2008

Dams : The Damned !

I am writing back on this unnerving issue of Dams, though I had written something on the same, in this post : Dams: boon or curse ?. Its been long since I rechecked, and hence I thought it would be better if I update you guys again.

Dam is going to be built- and thats for sure, looking at the desperate actions of our big and wigged politicians. Ya, the saviour of our AP. No body doubts that.
Public hearing were supposed to be conducted long back, but repeated oppositions of people of Dibang Valley forced the authorities to postpone the same.
Finally 11 May was fixed for the public hearing which saw vehement protests from all quarters of Roing public, spearheaded by zealous AIMSU(All Idu Mishmi Student Union)members. The boycotting of the public hearing was just a 'Cosmetic' formality that Govt wanted to have, so that they can further envisage on their plans to give a go ahead signal for the Dams.
(If you wish to read the full story,
click here). This news piece was covered by Veracity(a local daily of Roing).
Dibang Multipurpose project, is a known fait accompli, since the foundation stone for the project was already laid prior to the Public hearing, none other than the least expected person, our PM Manmohan Singh. And what's more ? Foundation stone and the pomp inauguration rituals , all in Itanagar, a corner of Arunachal, I would least expect the support against our movement for No Dams. (lest to say, No Mega Dams).
Not to hurt anyone from Itanagar, but the abject truth is, for most part of the truth, that all the Arunachali people wants Dam to be built in Dibang.

I am quite confident enough, they would have had some different view if Dam were to be built at their place. Anyway, thats deviating.

Dam statistics : a prelude.


One paisa/unit of power the 3000MW Dibang Multipurpose Project(DMP) is by what people have been lured, making them believe that the same amount would be invested on various local developmental aspects. Vagaries of promises, I would rather say !
We have been promised umpteen number of times, this or that govt would certainly pave in the developments that has so much shyed from us.
Certainly for people like us, who have been merely by stranded to watch amass few people, all of the supposed to be public funds, a promise of yet another probable upliftment would be a soothing effect.
Hydroelectric Project which as of now has been considered a booming business, owing to the facts that world at this moment is facing the severest crunch of Energy resources. Petrols hitting more than 100$ per barrel, depleting oil reserves and many other reasons, would obviously make the Govt to fund for further advanced research to come up with alternatives for the Oils as energy source. As of now, Hydroelectricity seems to be the cheapest and most reliable option. Profitable "Hydro dollars", thats something what people investing on the same can achieve.

But, should it be at the cost of people. Sovereignty and the mandatory obligations for the Govt is an outdated concept. Sovereignty further brings in Democracy as well, and hence the rights of every section of the society to oppose or accept, what they have been meted with!
It is estimated that a surplus of Rs8000 crore, would be our state govt's earning through the sale of electricity generated from all the Dams in Arunachal.

But, pondering on "how many Dams ?" would infact delight our unrelenting apetite to churn out more wealth.
Our ambitious Govt, for having suffered people's lamentations over the years wants to settle it right away. And ask how ?
Our State Government has envisaged plans to come up with more than 104 hydropower projects, which would total an estimated generation of 56000MW power, equaling one third of India's potential. Ya, you heard it right 56000MW.
Happy to learn that, or rather say Happy to have discovered our latent potential, which If it had not been our Govt's initiatives would have been an unknown thing for rest of our life.
From april 2007 to Feb 2008, around 38 projects have been signed with private companies, making it a
3 and half projects in a month.

Healthy revelations, is that ?
This much for the moment. I shall update it later.
:)

Read more...

Tuesday, October 02, 2007

Dams : Boon or a Curse ?

The need for development at the cost of some Tribal communities doesn't suffice for the National development on the long run, and neither it safeguards the people's right as profoundly stated in any of the Consitutional Dictionaries. But our incumbent, Stubborn, and corrupted politicians, seeing only the personal gain, with the meek propounded reasons of National developmentary works,somehow creates the Distorted Figure of Relative Low power production in the country as whole and offcourse not to forget the ever increasing numbers of power hungry industries all over the country. Ya, none denies here the Economy standout of India at this period, booming economy, surplus white collared job opportunities(BUT provided you're outside Arunachal pradesh). But why this special provision? My question here would be why Industrialization that has been a phenomenon post independence, has failed to dig a mark in Arunachal ,even after the so called, cliched , exagerrately falsifying....Glorious 50 years of Independence. Sheer example of colonial treatment? Is that?Transportation ... ?? I guess, one can't have that for excuse, seeing the present interest of NHPC and other big corporations who are willing to build the biggest dam of the world , provide cheap electricity , build good bridges, and the blah blahs of promising developmental activities, but at the cost of some Tribal communities losing their land and not to forget the Demographic distortion that it would pave forth to the Tribal dominated places.My another question here would be.... When a company(GOI owned) can promise at the span of 10 years, why Indian govt has failed to do so in the last 50yrs? Now, if you say, give and take policy... and Govt means Business here, then the balanced fulcrum of the So much Blasted Indian Democracy would turn to just one.
Just a reminder here... 50 years ago, North East had witnessed one of the biggest Earthquake in the world's history, 8.7 richter, and more than 50% of the Idu Mishmi population were killed in that. (just pertaining to my community , IDU , as the Dams are being built there). 50+ years now, no such major Earthquake has been witnessed yet, so does that implicate we won't see another such major Earthquake, 50 or 100 or 200 years from now ? That would be utterly ridiculous, given the fact that NE lies in a Seimically active zone.NHPC , now shows us the prospects of creating Dam, whose benefit we could see through burgeoning Industries that would place its base here, and not to mention the Capital inflows that would be tandem with the Business developments. Contractors would be frenzied by the so much lauded statements in their(NHPC's ) Environmental Impace Assesment report(EIA) that most of the contractorial work would be alloted to the Native of this place, till the Dam construction gets over.The Irony of this special provisions would be that, We(the Native) would be Time Scaling the existence of our community for another 50 or 100 years(provided no major earthquake takes place within it) for the sake of developmental aspects that we could enjoy for another 20 or 30 years. Well, Basics of doing Business fails here !! So where's the justice ?Now coming to seimic proof megastructures.... Till date there's no such technology that can predict when and where and in what scale the Earthquake would occur, so the Question of creating any Megastructures which is earthquake proof would be out of Topic. If this had not been true, we wouldn't have lost so many lives, to just Tsunamis.
To peoples not residing in Dibang valley, the displacement of some 2000 or 3000 peoples from their ancestral place for the cause of India, which boasts of billion population might seem a very small sacrifice. But, I request you all the pro dam peoples... visit our dibang valley.... look into the the traditions and cultures that we subscribe to, and our love for our ancestral land.... Question us, if we want the Dam ? You'll have our answer. This would be our first instance of being anti development...but quite content with the modest life.... and booming indian economy , light years away from us. We're happy.Just pondering....how much National developmental work would it have been.... a Dam on Yamuna (not far from TAJ MAHAL).
When we talk about the economic viability of the project taking care of the safety aspect, then Economics not affecting dam design and hence dam safety is,at best, Naive. To a certain degree, an increase in dam safety involves an increase in cost. For every dam project, a balance has to be found between dam safety and economy. And for this obvious reason, a slight compromise can cause havoc...not now but in future for sure. It is also not realistic to hold that all engineers in all cases follow engineering codes of ethics. Further there is no internationally accepted code of ethics for dam builders, rather a mish-mash of national and state engineering codes with ambiguous applicability to mega projects.Many of the methods to prolong dam lifespan are largely unproven, will in many cases not be economically viable, and will rarely be able to prolong dam life indefinitely. So, the question that moots out is...If there would be safe dam decomissioning after it expires ? To answer that, maybe the Grandchildren of Dam builders should be liable since it definitely wont happen in a serious way during their lives.Given the attitude of centre toward AP presently and offcourse to follow the suit in future, will for sure leave the dam as it is owing to the huge expenditure involved in Decommisioning it. So, apathy of the central govt toward Arunachal is bound to reflect in any domain of timescale, owing to the miniscule role AP has in formation of strong Central govt.
Few of the excerpts from the memoradum that we'ad submitted to the CM in protest of Dam projects in Dibang valley.Only the indigenous populations are victims of pre-dam and post dam construction disaster.More than 4,00,000 sqkm - have been inundated by reservoirs worldwide. This represents .3 percent of the world's land area, but the significance of the loss is greater than the figure suggests as river valley land provides the world's most fertile farmland, and most diverse forests and wetland ecosystems.More than 13,500 people have been swept to their deaths by the roughly 200 dams outside China which have collapsed or been overtopped during the 20th century. Two large Dams which burst when a massive typhoon hit the chinese province of Henan in Aug 1975 left an estimated 80000 to 230,000 dead. This disaster was kept secret by the chinese govt and was only revealed to the outside world in 1995. People have also died in Earthquakes caused by the great weight of water in large reservoirs. An earthquake of magnitude of 6.3 richter caused by Koyna Dam(INDIA) in 1967 killed around 180 peoples.Impact on demographic profile, health and culture of indigenous population"large Dams have had serious impact on lives,livelihood, cultural and spiritual existence of indigenous and tribal people due to neglect and lack of capacity to secure justice because of structural inequities,cultural dissonance,discrimination and economic and political marginalization,indigenous and tribal people have suffered disproportionately from the negative impacts of large dams while often being excluded from sharing in the benefits" as per the WORLD COMMISSION ON DAMS.
HEALTH: Dams can have significant adverse health outcomes for local population and downstream communities. In recent years the high incidents of HIV/AIDS in construction and settlement areas is a growing concern. Destruction of community productive bases in agrculture and fisheries can give rise to food shortages,leading to hunger and malnutrition. The Sikkim state has had experienced this serious threat.HIGH SEISMICITY: Dr.K.S.Valdiya,"It would be imprudent to go in for high dams in Arunachal's highly earthquake prone region of active faults." (keynote address in workshop on environmental planning and sustainable developments in AP in Dec 99).The Northeast is a geologically fragile area and is seimically active. Well known Dr.K.S.Valdiya, while referring to the geological set up of Arunachal says:"Owing to the extremely active geodynamic condition of the terrain, even the slightest tampering with teh ecological geological balance can initiate environmental changes,likely to assume alarming proportions eventually. There is an imperative need for extraordinary care when it comes to modifying topography by excavation,placing loads of water and sediments in river impoundments, changing groundwater circulation through road cutting,removing protective forest cover,etc".Usually, when seismicity is discussed in relation to dams, the factors discussed are reservoir induced seimicity and direct damage to the dam due to an earthquake. Civil Engineers are quick to point out that a dam will survive upto 9 or 10 on richter scale. However seismic activity may cause changes in the geophysical enviroment and the river system, which may have a serious impact on the viability of a project as several basic parameteres vis-a-vis the regime of rivers and the morphology and behavious of channels may change.The last two major earthquakes in the region (1897 and 1950)caused landslides on the hill slopes including the blockage of river courses, flash floods due to sudden bursting of landslide-induced temporary dams, raising water to a much dangerous level.
Is it FLOOD CONTROLLER ?While large dams could regulate regular annual floods if an adequate flood cushion is provided , they often fail to hold back exceptionally large floods. Dams can also worsen flooding by reducing the capacity of the riverbed downstream. They can also cause serious floods when reservoir operators make sudden releases of water, something which was experienced in more than one case by the ASSAM Valley in the monsoon of 2004( Kopili hydropower reservoir run by NEEPCO).The eastern himalyan rivers experience great variation in minimm and maximum flows and is prone to sudden increased water flows due to intense precipitation in a very short time, which increases risks of such releases from dams on the river. Unfortunately, the Environmental Risk Assessment done for projects such as Lower subansiri and Middle siang projects only looks at the "DAM BREAK ANALYSIS" scenario and completely ignore other environmental risks which can pose challenges to the viability of the project, both interms of its performance as well the impacts it causes downstream.In the USA and France, Dams have been decommissioning to restore key environmental values often related to migratory fishes, and often as a condition of project relicensing.Whereas Arunachal pradesh is covered with forests of exceptionally high biodiversity. There are 4000 to 5000 species of vascular plants per 10000 sqkm. The second richest biodiversity zone in the global context. And as per the EIA report submitted for the Proposed Dibang hydro project, NHPC mentioned that Dibang valley or the submerging area to be precise, has only 2 species of Butterflies. Seems amusing. Supporters of large dams point out that big dams do not have only negative impacts but also positive ones. Once again, however, the evidence is scanty in this respect. Whatever be the negative and positive impacts, one striking fact of india's river valley projects is the absence of comprehensive impact assessment, both pre and post construction.
ACTUAL PERFORMANCE OF LARGE DAMS IN INDIA .In a recent report for the world commission on dams(WCD), an exhaustive look at the facts and figures available establishes that until 1978, most dams were not assessed for their environmental and social impacts. Even when they began to be assessed, alternatives to the dam were never assessed and mostly not even considered. Also, that the current system of granting environmental clearances is subject to all sorts of political and admistrative pressures, resulting in clearances being granted to projects without assessing their impacts or even when they are non-viable.Dam failure and emergency releases of water pose a threat to downstream populations. Again though no comprehensive data are available, the havoc wreaked downstream by, the Bhakra Dam (1970s and in 1988) and the Rihand dam in 1997 is well known. Dr. Y.k.Murthy, a former chairman of Central water and power commission has concluded that, of the 131 dams studied by him, 36man;ifested distress , in 20 the spilways were inadequate and in 25 the freeboards were inadequate, all compromising the safety of dam. In 90 of the dams studied, there was no emergency reservoir operations plan.Perhaps the most heart rending aspect of large dams is the displacement of Human populations. Again no comprehensive data are available. A study by CWC, of 54 projects, showed a per dam submergence of 24555ha. The same study showed a per hectare displacement of 1.1person. If one were to extrapolate these figures to the 4291 large dams built in India, the total displacement figure would be 11.5 crore in the last 100 years or so. So clearly, the major costs of large dams are borne by the poor and the weak. But who are the major beneficiaries ? The irrigation benefits go to those downstream and , among them, disproportionaftely to the large farmers. Similarly, the peaking power that dam provide goes primarily to meet the peak demand of the urban rich and the industry. What does the Nation gain as a whole ?
According to the WCD study, large dams after 1990 show no economic benefits over costs and only have a distributional function, where " the benefits are reaped by farmers and others in the command areas and the costs are borne by the Society at large, tax payers and the project affected people. So we have a situation today where thousands of dams have been built, with little or no environmental assessments and safeguards, and huge adverse social impacts. Millions of hectares of forests have been destroyed, huge areas have become waterlogged , incidence of water borne diseases has increased, lakhs of peoples have been thrown out of their homes,mainly TRIBALS, the poor and the weak. And all this to create structures that, even without acknowledging most of the environmental and social costs, add not a rupee worth of value to the Indian economy. All they do is redistribute the existing resources so that the poor are further deprived and the relatively well off gets the benefits.

List to watch out for !
MAJOR HYDRO PROJECTS IN ARUNACHAL PRADESH
PART-I
No. Name of Project District Capacity Developer Status (in MW)
1 SIYOM west siang 1000 Reliance MOA signed
2 TATO-II west siang 700 Reliance MOA signed
3 NAYING west siang 1000 D S Construction MOA signed
4 HIRONG west siang 500 Jai Prakash MOA signed
5 SIANG LOWER east siang 1600 Jai Prakash MOA signed
6 NYAMJUNGCHHU-I (tawang) 98 Bhilwara Energy MOA signed
7 NYAMJUNGCHHU-II (tawang) 97 Bhilwara Energy MOA signed
8 NYAMJUNGCHHU-III (tawang) 95 Bhilwara Energy MOA signed
9 TAWANG-I (tawang) 750 NHPC MOA signed
10 TAWANG-II (tawang) 750 NHPC MOA signed
11 KALAI-I (anjaw) 1400 Mountain Fall India MOA signed
12 KALAI-II (anjaw) 1200 - tender called
13 HUTONG-I (anjaw) 588 - tender called
14 HUTONG-II(anjaw) 1250 Mountain Fall India MOA signed
15 BADAO (east kameng) 60 - CEA clearance awaited
16 KAMENG DAM(east kameng) 600 KSK Electricity MOA signed
17 KAPAK LEYAK(east kameng) 160 - S&I Stage-II
18 KAMENG-I (east kameng) 1120 NEEPCO MOA signed
19 TALONG (east kameng) 160 GMR Energy MOA signed
20 DIBBIN (west kameng) 125 KSK Electricity MOA signed
21 KAMENG-II (west kameng) 600 Mountain Fall India MOA signed
22 KAMENG (west kameng) 600 NEEPCO under construction
23 RANGANADI-I lower subansiri 405 NEEPCO COMPLETED
24 RANGANADI-II lower subansiri 130 NEEPCO CEA clearance awaited
25 SUBANSIRI LOWER(lower subansiri) 2000 NHPC Case in Supreme Court
26 SUBANSIRI MIDDLE(lower subansiri) 1600 NHPC Restricted by Supreme Court
27 SUBANSIRI UPPER(upper subansiri) 2000 NHPC Restricted by Supreme Court
28 OJU-I (upper subansiri) 700 -- Restricted by Supreme Court
29 OJU-II (upper subansiri) 1000 -- Restricted by Supreme Court
30 PARE (papumpare) 110 NEEPCO MOA signed
31 LOHIT (lohit) 3000 -- S&I Stage-II
32 DEMWE(lohit) 3000 -- tender called
33 DIBANG(lower dibang valley) 3000 NHPC MOA signed
34 SISSIRI(lower dibang valley) 222 -- tender called
35 AMULIN(dibang valley) 420 -- tender called
36 EMINI (dibang valley) 500 -- tender called
37 ANGOLINE(dibang valley) 375 -- tender called
38 MITHUNDON(dibang valley) 400 -- tender called
39 ETABU (dibang valley) 165 -- tender called
40 MALINYE(dibang valley) 335 -- tender called
41 EMRA-I(dibang valley) 275 -- tender called
42 EMRA-II(dibang valley) 390 -- tender called
43 ELANGO(dibang valley) 150 -- tender called
44 ETALIN(dibang valley) 4000 NTPC MOA signed
45 ATTUNLI(dibang valley) 500 NTPC MOA signed
46 NIARE -- 800 - S&I Stage-II
47 NABA -- 1000 - S&I Stage-II

"TOTAL INSTALLED CAPACITY OF 40930 MW "

Read more...